Question: Given the following project: 1. Develop a time limited resource profile chart assuming unlimited resource availability. That is, determine the resource requirement on a weekly
Given the following project: 1. Develop a time limited resource profile chart assuming unlimited resource availability. That is, determine the resource requirement on a weekly basis if the project is to be completed in the minimum time. 2. Develop a resource-constrained schedule using the sequential heuristic.
|
Activity |
Predecessor | Duration (week) | Required No. of Workers |
| 1 | - | 3 | 2 |
| 2 | - | 2 | 1 |
| 3 | 2 | 3 | 2 |
| 4 | 2,5 | 4 | 2 |
| 5 | 1 | 4 | 1 |
| 6 | 3,4,1 | 3 | 1 |
| 7 | 3 | 4 | 2 |
| 8 | 5 | 3 | 1 |
Assume the followings:
- The original relationships of the network cannot be violated.
- Scheduling priority for each activity is determined via the following rules
- least total slack
- early start time
- smallest duration
- maximum resource level
- once an activity is scheduled it continues without interruption
The available resource is three units