Question: Given the following project: 1. Develop a time limited resource profile chart assuming unlimited resource availability. That is, determine the resource requirement on a weekly

Given the following project: 1. Develop a time limited resource profile chart assuming unlimited resource availability. That is, determine the resource requirement on a weekly basis if the project is to be completed in the minimum time. 2. Develop a resource-constrained schedule using the sequential heuristic.

Activity

Predecessor

Duration

(week)

Required No.

of Workers

1

-

3

2

2

-

2

1

3

2

3

2

4

2,5

4

2

5

1

4

1

6

3,4,1

3

1

7

3

4

2

8

5

3

1

Assume the followings:

  • The original relationships of the network cannot be violated.
  • Scheduling priority for each activity is determined via the following rules
  • least total slack
  • early start time
  • smallest duration
  • maximum resource level
  • once an activity is scheduled it continues without interruption

The available resource is three units

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!