Question: Given the following project: begin { tabular } { | c | c | l | } hline Activity & Time & Predecessor

Given the following project:
\begin{tabular}{|c|c|l|}
\hline Activity & Time & Predecessor \\
\hline A & 3 & None \\
\hline B & 4 & None \\
\hline C & 2 & A \\
\hline D & 4 & B \\
\hline E & 1 & B \\
\hline F & 6 & C \\
\hline G & 3 & D,E \\
\hline H & 5 & F \\
\hline I & 2 & G \\
\hline J & 3 & H, I \\
\hline K & 4 & J \\
\hline
\end{tabular}
Determine actixity E slack
Alternatives:
A.4 weeks
B.3 weeks
C.2 weeks
D.1 week
E.0