Question: Given the following project data that include a table of activities, durations in days, precedence, and costs. A field report was issued at the end

Given the following project data that include a table of activities, durations in days, precedence, and costs.

A field report was issued at the end of DAY 8 as shown. Compute the required values in the EV analysis and fill in the sky-blue blanks for activities C and E. Please, use only two decimal points in your calculations.

Planned Values

Field Report day 8

Activity

Predecessor

Duration(days)

Cost/day

Total Cost

Activity

% Complete

Incurred Cost

A

2

$300

$600

A

100%

$600

B

A

3

$400

$1,200

B

100%

$1,400

C

B

3

$400

$1,200

C

50%

$800

D

B

2

$200

$400

D

100%

$600

E

D

3

$100

$300

E

50%

$100

Activity

AC

EV

PV

CPI

CV

SPI

SV

A

B

C

D

E

1. Activity C CPI :

2. Activity C CV :

3. Activity C SPI:

4. Activity C SV:

5. Activity E CPI:

6. Activity E CV:

7. Activity E SPI:

8. Activity E SV:

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!