Question: Given the following project data that include a table of activities, durations in days, precedence, and costs. A field report was issued at the end
Given the following project data that include a table of activities, durations in days, precedence, and costs.
A field report was issued at the end of DAY 8 as shown. Compute the required values in the EV analysis and fill in the sky-blue blanks for activities C and E. Please, use only two decimal points in your calculations.
| Planned Values | Field Report day 8 | |||||||
| Activity | Predecessor | Duration(days) | Cost/day | Total Cost |
| Activity | % Complete | Incurred Cost |
| A |
| 2 | $300 | $600 | A | 100% | $600 | |
| B | A | 3 | $400 | $1,200 | B | 100% | $1,400 | |
| C | B | 3 | $400 | $1,200 | C | 50% | $800 | |
| D | B | 2 | $200 | $400 | D | 100% | $600 | |
| E | D | 3 | $100 | $300 | E | 50% | $100 | |
| Activity | AC | EV | PV | CPI | CV | SPI | SV | |
| A |
|
|
|
|
|
|
| |
| B |
|
|
|
|
|
|
| |
| C |
|
|
|
|
|
|
| |
| D |
|
|
|
|
|
|
| |
| E |
|
|
|
|
|
|
| |
1. Activity C CPI :
2. Activity C CV :
3. Activity C SPI:
4. Activity C SV:
5. Activity E CPI:
6. Activity E CV:
7. Activity E SPI:
8. Activity E SV: