Question: Given the following project information, a) draw an Activity-On-Node project network. b) compute the Earliest Start time, Earliest Finish time, Latest Finish time, Latest Start

Given the following project information,

a) draw an Activity-On-Node project network.

b) compute the Earliest Start time, Earliest Finish time, Latest Finish time, Latest Start time and Total Float time and Free Float time for each activity.

c) identify the critical path.

Please mark time variables for each activity as

Given the following project information, a) draw

Activity Predecessor Duration Activity Predecessor Duration a -- 3 i f 4 b 5 g.f 5 j k a 4 h 4 d a.b 7 1 7 ij k,1 e b 8 m 2 f 8 c.d d bo 6 h 4 ES TF EF Please mark time variables for each activity as Activity Duration LS FF; LF

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!