Question: Given the following project network and baseline information, complete the form to develop a status report for the project at the end of period 4
Given the following project network and baseline information, complete the form to develop a status report for the project at the end of period 4 and the end of period 8.
From the data you have collected and computed for periods 4 and 8, what information are you prepared to tell the customer about the status of the project at the end of period 8?



\f\fEnd of Period 4 Task Actual % Complete EV AC PV CV SV A Finished - 300 400 B 50% - 1000 800 O 33% - 500 600 D 0% 0 E 0% Cumulative Totals End of Period 8 Task Actual % Complete EV AC PV CV SV A Finished 300 400 B Finished - 2200 2400 Finished - 1500 1500 D 25% 300 0 E 33% 300 F 0% 0 Cumulative Totals
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
