Question: Given the following project network, baseline and status information, develop status reports for periods 2, 6, 8 and complete performance indexes tables. Prepare the budget

Given the following project network, baseline and status information, develop status reports for periods 2, 6, 8 and complete performance indexes tables.

Prepare the budget plan.

Calculate EAC at each period.

Also, comment on the project status at completion.

Activity ID Rule Imm. Pred. Time Cost('00)
A Proptionate - 4 40
B 50-50 - 5 32
C Prop. A 4 48
D 50-50 A,B 5 18
E 0-100 B 3 28
F Prop. C,D,E 2 40
Total 206