Question: Given the following project network, baseline and status information, develop status reports for periods 2, 6, 8 and complete performance indexes tables. Prepare the budget
Given the following project network, baseline and status information, develop status reports for periods 2, 6, 8 and complete performance indexes tables.
Prepare the budget plan.
Calculate EAC at each period.
Also, comment on the project status at completion.
| Activity ID | Rule | Imm. Pred. | Time | Cost('00) |
| A | Proptionate | - | 4 | 40 |
| B | 50-50 | - | 5 | 32 |
| C | Prop. | A | 4 | 48 |
| D | 50-50 | A,B | 5 | 18 |
| E | 0-100 | B | 3 | 28 |
| F | Prop. | C,D,E | 2 | 40 |
| Total | 206 |