Question: Given the following project network, baseline, and status information, develop status reports for periods 14. Report the final SV, CV, CPI, and PCIB. Based on

Given the following project network, baseline, and status information, develop status reports for periods 14.

Report the final SV, CV, CPI, and PCIB.

Based on your data, what is your assessment of the current status of the project? At completion?

Given the following project network, baseline, and status information, develop status reports

for periods 14. Report the final SV, CV, CPI, and PCIB. Based

\begin{tabular}{|l|l|l|} \hline 0 & 1 & 2 \\ \hline 1 & & 1 \\ \hline 1 & 2 & 3 \\ \hline \end{tabular} \begin{tabular}{|l|l|l|} \hline 2 & 4 & 4 \\ \hline 1 & & 1 \\ \hline 3 & 2 & 5 \\ \hline \end{tabular} \begin{tabular}{|l|l|l|} \hline 0 & 2 & 3 \\ \hline 0 & & 0 \\ \hline 0 & 3 & 3 \\ \hline \end{tabular} \begin{tabular}{|l|l|l|} \hline 3 & 5 & 5 \\ \hline 0 & & 0 \\ \hline 3 & 2 & 5 \\ \hline \end{tabular} \begin{tabular}{|l|l|l|} \hline 5 & 7 & 6 \\ \hline 0 & & 0 \\ \hline 5 & 1 & 6 \\ \hline \end{tabular} \begin{tabular}{|l|l|l|} \hline 0 & 3 & 2 \\ \hline 0 & & 0 \\ \hline 0 & 2 & 2 \\ \hline \end{tabular} \begin{tabular}{|l|l|l|} \hline 2 & 6 & 5 \\ \hline 0 & & 0 \\ \hline 2 & 3 & 5 \\ \hline \end{tabular} LEGEND \begin{tabular}{|l|l|l|} \hline ES & ID & EF \\ \hline SL & & SL \\ \hline LS & DUR & LF \\ \hline \end{tabular} Status Report: Ending Period 1 (\$000) \begin{tabular}{l} Task \\ 1 \\ 2 \\ 3 \\ Cumulative Totals \\ \hline Status Report: Ending Period 2 \end{tabular} T) 1 2 3 %CompleteFinished80%75%EVAC1314835PVCVSV Status Report: Ending Period 3 (\$000)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!