Question: Given the following project network, baseline, and status information, develop status reports for periods 8 and 12 and complete the performance indices table. Calculate the

Given the following project network, baseline, and status information, develop status reports for periods 8 and 12 and complete the performance indices table. Calculate the EAC and the VAC. Based on your data what is your assessment of the current status of the project? At completion?

Given the following project network, baseline, and status information, develop status reports

for periods 8 and 12 and complete the performance indices table. Calculate

End of Period 8 \begin{tabular}{|c|c|c|c|c|c|c|} \hline \multirow{2}{*}{ Task } & Actual % & EV & AC & PV & CV & SV \\ \cline { 2 - 6 } & Complete & $ & $ & $ & $ & $ \\ \hline A & Finished & & 300 & & & \\ \hline B & Finished & & 2200 & & & \\ \hline \end{tabular} End af Period 8 \begin{tabular}{|c|c|c|c|c|c|c|} \hline & Actwal X & EV & AC & PV & CV & SV \\ \hline Task & Conplete & 5 & $ & 5 & 5 & 5 \\ \hline A & Finithed & & 300 & & & \\ \hline B & Aniched & & 2200 & & \\ \hline C & Finithed & & 1500 & & \\ \hline D & 25% & & 300 & & \\ \hline E & 300 & & 300 & & \\ \hline F & OS & & 0 & \\ \hline Cumulative Totals & & 4600 & \\ \hline \end{tabular} Fnd of Period 12 \begin{tabular}{|l|l|l|l|l|l|l|} \hline Aeriod & EV & AC & PV & CFI & SPI & PCie \\ \hline E & & & & & & \\ \hline 12 & & & & & & \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!