Question: Given the following project network, baseline and status information, develop status reports for periods 4 and period 8 and complete the performance indices table. Based

Given the following project network, baseline and status information, develop status reports for periods 4 and period 8 and complete the performance indices table.

Based on your data, what is your assessment of the current status of the project? At completion?

Given the following project network, baseline and

Given the following project network, baseline and

LEGEND ESD EF SL LS DUR LF SL 2 B 8 8 D 12 0 0 0 268 0 A 2 0 0 2 2 2 12 | F 15 0 12 3 15 0 27 2 2 5 7 E10 2 2 Project baseline (PV) (in $) Task DUR DUR ES LF SL 15 A 2 0 2 0 B 6 2 8 0 2400 5 2 9 Budget (PV) 6 1 2 3 4 5 6 7 8 9 10 11 12 13 14 400 200 200 200 600 200 600 200 600 2 1500 200 400 500 100 300 400 400 400 400 300 400 200 o 600 200 100 300 Period PV total 200 200 400 1000 700 700 500 900 900 900 400 400 200 100 300 Cumulative PV total 200 400 300 100 2500 3200 3700 450054006000640068007000 7100 7400 D 4 8 12 0 1600 E 3 7 900 F 3 12 15 EV SV PV 400 End of Period 4 Task A B D E Cumulative Totals Actual % Complete Finished 50% 33% 0% 0% AC 300 1000 500 0 800 600 End of Period 8 EV AC PV CV SV Task Actual % Complete A Finished 300 400 B Finished 2200 2400 Finished 1500 1500 D 25% 300 0 E 33% 300 F 0% 0 Cumulative Totals

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!