Question: Given the following project network: Process diagram for 1 5 . 9 ( Algo ) . Process begins with Task A of 5 weeks. Then

Given the following project network:
Process diagram for 15.9(Algo). Process begins with Task A of 5 weeks. Then comes Task B of 6 weeks and Task C of 7 weeks. Task B of 6 weeks goes on to Task D of 5 weeks. This ends with Task F of 2 weeks. task C of 7 weeks goes on to Task D of 5 weeks and Task E of 4 weeks. Task E of 4 weeks ends with Task F of 2 weeks.
a-1. Identify the critical path.
a-2. Identify the earliest start and finish for each task.
b. Calculate the slack for every project activity.