Question: Given the following project network: TaskB 3 weeks Task D 6 weeks Task A 7 weeks Task F 5 weeks Task C 6 weeks Task

Given the following project network: TaskB 3Given the following project network: TaskB 3

Given the following project network: TaskB 3 weeks Task D 6 weeks Task A 7 weeks Task F 5 weeks Task C 6 weeks Task E 4 weeks a-1. Identify the critical path. A-C-E-F O A-B-D-F O A-C-D-F a-2. Identify the earliest start and finish for each task. (Leave no cells blank - be certain to enter "0" wherever required.) Task Earliest Start Earliest Completion Immediate Predecessors None A weeks weeks B weeks weeks A weeks weeks 11111 D |B, C weeks E weeks weeks weeks weeks F D, E weeks b. Calculate slack for every project activity. (Leave no cells blank - be certain to enter "O" wherever required.) Task Latest Completion Latest Start Slack F Immediate Successors None F F E D TITI D, E B D A B, C

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!