Question: Given the following project plan ID Task Predecessor Duration (days) 3 Budget ($) 640.02 A Hardware selection Start B Software design Start 14 426.68 Install

Given the following project plan ID Task

Given the following project plan ID Task Predecessor Duration (days) 3 Budget ($) 640.02 A Hardware selection Start B Software design Start 14 426.68 Install hardware A 3 320.01 D Coding B 7 426.68 E Testing B 3 320.01 F System Start 10 1066.7 documentation G User training E,F 2 320.01 H Deploy system C,D 5 213.34 Table 1 Tasks 1. Input the information from the table above and generate the Gantt Chart, and include it in your report. Consider the start of the project October 1st 2021, and weekends as normal work days