Question: Given the following small project, the critical path is ________ days. Activity Immediate Predecessor Time (days) A - 10 B - 4 C A, B
Given the following small project, the critical path is ________ days.
| Activity | Immediate Predecessor | Time (days) |
| A | - | 10 |
| B | - | 4 |
| C | A, B | 6 |
a. 14
b.10
c.20
d.16
NOTE PLEASE SHOW ME CALCULATION