Question: Given the following small project, the critical path is ________ days. Activity Immediate Predecessor Time (days) A - 10 B - 4 C A, B

Given the following small project, the critical path is ________ days.

Activity

Immediate

Predecessor

Time

(days)

A

-

10

B

-

4

C

A, B

6

a. 14

b.10

c.20

d.16

NOTE PLEASE SHOW ME CALCULATION