Given the following task time estimates (HOURS),
TaskTimePredecessorA40B20C25AD19A, BE25C, DF24EG18F
a. How long is the project length? [ Select ]["122.00","134.83","127.45","132.00","135.78"].
b. What tasks form the critical path? [ Select ]["B, D, E, F, G","A, C, E, F, G","A, D, E, F, G","B, C, D, E, F, G","A, B, C, E, F, G"]
c. What is the LS/LF for activity D.?[ Select ]["44 and 55","46 and 65","65 and 90","50.19 and 7.08","34.56 and 4.78"].
d. How much slack is there in activity C?[ Select ]["12 hours", "6 hours", "29 hours", "0","8.34 hours"] How much slack in activity D?[ Select ]["6 hours", "28 hours", "26 hours", "0, it is on the critical path", "5 hours"]
e. What if activity D. was delayed by 7 hours, what would be the project length and critical path? [ Select ]["132 hours; A, C, E, F, G","134 hours; A, C, E, F, G","no change in either the critical path or project length", "130 hours; B, C, E, F, F","133 hours; A, D, E, F, G"]
f. Referring to letter e., how much slack would be in activity B.?[ Select ]["26 hours", "0(zero), it is now on the critical path", "8 hours", "20 hours", "6 hours"]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!