Question: Given the following task time estimates (HOURS), Task Time Predecessor A 40 B 20 C 25 A D 19 A, B E 25 C, D
Given the following task time estimates (HOURS),
| Task | Time | Predecessor |
| A | 40 | |
| B | 20 | |
| C | 25 | A |
| D | 19 | A, B |
| E | 25 | C, D |
| F | 24 | E |
| G | 18 | F |
a. How long is the project length?
b. What tasks form the critical path?
c. What is the LS/LF for activity D.?
d. How much slack is there in activity C?
How much slack in activity D?
e. What if activity D. was delayed by 6 hours, what would be the project length and critical path?
f. Referring to letter e., how much slack would be in activity B.?
*Please show work in excel (formulas)