Question: Given the following task time estimates (HOURS), Task Time Predecessor A 40 B 20 C 25 A D 19 A, B E 25 C, D

Given the following task time estimates (HOURS),

Task Time Predecessor
A 40
B 20
C 25 A
D 19 A, B
E 25 C, D
F 24 E
G 18 F

a. How long is the project length?

b. What tasks form the critical path?

c. What is the LS/LF for activity D.?

d. How much slack is there in activity C?

How much slack in activity D?

e. What if activity D. was delayed by 6 hours, what would be the project length and critical path?

f. Referring to letter e., how much slack would be in activity B.?

*Please show work in excel (formulas)