Question: Given the following task, times, and sequence, develop a balanced line capable of operating with a 1 0 - minute cycle time at Dave Visser's

Given the following task, times, and sequence, develop a balanced line capable of operating with a10-minute cycle time at Dave Visser's company.
Task
Time(minutes)
Element Predecessor
Task
Time(minutes)
Element Predecessor
A
3
-
E
3
C
B
5
A
F
3
B, D
C
7
B
G
5
D
D
5
-
H
6
G
Part 2
a) Choose the correct precedence diagram below.
A.
A
B
D
F
G
H
C
E
B.
A
B
D
F
G
H
C
E
Your answer is correct.C.
A
B
D
F
G
H
C
E
D.
A
B
D
F
G
H
C
E
Part 3
b) Assign tasks to the minimum feasible number of work stations according to the greatest time remaining(ranked positional weight) decision rule. Complete the table below.
Station
Tasks
1
A,
H
F
C
D
2
H
B
F
D
, G
3
C,
H
B
F
D
4
B
H
D
F
, E

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!