Question: Given the following task, times, and sequence, develop a balanced line capable of operating with a 1 0 - minute cycle time at Dave Visser's

Given the following task, times, and sequence, develop a balanced line capable of operating with a10-minute cycle time at Dave Visser's company.
Task
Time(minutes)
Element Predecessor
Task
Time(minutes)
Element Predecessor
A
3
-
E
3
C
B
5
A
F
3
B, D
C
7
B
G
5
D
D
5
-
H
6
G
Part 2
a) Choose the correct precedence diagram below.