Question: Given the following, the efficiency and balance delay are as follows respectively: Cycle Time = 15 min Total Time = 45 min # of Work

Given the following, the efficiency and balance delay are as follows respectively: Cycle Time = 15 min Total Time = 45 min # of Work Stations = 5