Question: Given the following three jobs ( processes ) , determine the time when P 2 finishes assuming round - robin scheduling with a quantum of

Given the following three jobs (processes), determine the time when P2 finishes assuming round-robin scheduling with a quantum of 10CPU units.
\table[[Process,Arrival Time,CPU Burst time,Priority],[P1,5,10,2],[P2,15,5,1],[P3,0,20,3]]
20
25
35
10
5
0