Question: Given the following time estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the expected time (te) estimate? Question 19Select

Given the following time estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the expected time (te) estimate? Question 19Select one: a. 6 days b. 4 days c. 3 days d. 4.5 days e. 1 week, not counting weekends