Question: Given the following, use Microsoft Project to develop the initial schedule. ( For consistency, start 2 Jan 2 0 2 4 ) Activity Estimated duration

Given the following, use Microsoft Project to develop the initial schedule. (For consistency, start 2 Jan
2024)
Activity Estimated duration Predecessors Budget
A1 DesignProjectA 4 weeks None $12 k
A2 ProductionProjectA 3 weeks A1 $7.5 k
A3 TestingProjectA 2 weeks A2 $8 k
A4 InstallProjectA 1 week A3 $2 k
B1 DesignProjectB 3 weeks A1 $9 k
B2 ProductionProjectB 3 weeks A2, B1 $7.5 k
B3 TestingProjectB 1 week A3, B2 $4 k
B4 InstallProjectB 1 week A4, B3 $2 k
C1 DesignProjectC 1 week B1 $3 k
C2 ProductionProjectC 2 weeks B2, C1 $5 k
C3 TestingProjectC 1 week B3, C2 $4 k
C4 InstallProjectC 1 week B4, C3 $2 k
Update in Microsoft Project and display status as of 8 weeks into the project.
Activity Actual as of 8th week Actual Spent as of 8th week
A1 DesignProjectA Completed in week 4 $12K
A2 ProductionProjectA Completed in week 7 $10K
A3 TestingProjectA 50% complete in week 8 $2K
A4 InstallProjectA Not started
B1 DesignProjectB Completed in week 8 $12K
B2 ProductionProjectB Not started
B3 TestingProjectB Not started
B4 InstallProjectB Not started
C1 DesignProjectC Not started
C2 ProductionProjectC Not started
C3 TestingProjectC Not started
C4 InstallProjectC Not started
Print off the original Gantt chart, as well as an updated Gantt chart as of week 8.
Comment on schedule, budget status
(I would not use Microsoft Project to deal with the budget, but rather read and think)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!