Question: Given the improvement curve data calculate the cost objective for unit #8 labor hours for unit #4 120 hours labor hours for unit #1 160

Given the improvement curve data calculate the cost objective for unit #8

labor hours for unit #4 120 hours

labor hours for unit #1 160 hrs

rate of improvement 10%

improvement curve slope 90%