Question: Given the information below: Activity Immediate Predecessor(s) Pessimistic Probable Optimistic A -- 13 8 6 B -- 7 3 1 C A 15 11 7
Given the information below:
Activity
Immediate Predecessor(s)
Pessimistic
Probable
Optimistic
A
--
13
8
6
B
--
7
3
1
C
A
15
11
7
D
A, B
9
4
2
E
C
7
5
3
F
D
10
7
5
Draw a network diagram; what is the critical path? (5 marks)
Calculate the expected duration of each activity; remember to show your formulas and calculations. (15 marks)
Activity
Expected Time
Variance of time
Standard Deviation
ES
EF
LS
LF
Slack
A
B
C
D
E
F
Calculate the expected duration and variance of the critical path, and the standard deviation; remember to show your formulas and calculations. (5 marks)
Use exponential smoothing with trend adjustment to forecast deliveries for period 4. Let alpha = 0.4, beta = 0.2, and let the initial trend value be 4 and the initial forecast be 200. Remember to show your formula and calculations. (5 marks)
Period
Actual
Demand
Forecast
Trend
FIT
1
200
2
212
3
214
4
222
A swim club is designing a new pool to replace its old pool. The new pool would need to last for 10 years since the club is planning on relocating after 10 years. A concrete shell would cost $100,000 and last for all 10 years. Another option is to install a vinyl liner that would cost only $90,000 to install. However, the vinyl is not guaranteed to last for all 10 years and has a 60% chance of breaking down. Repair of the vinyl would cost $40,000 and would extend the life of the vinyl liner to the 10-year mark. If both options are acceptable to the swim club, which one minimizes their cost?
Draw a decision tree. (5 marks)
Calculate the EMV(s); which one should they choose? (5 marks)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock