Question: Given the information below, determine the following: ( i ) Processing sequence using ( 1 ) SPT and ( 2 ) EDD. ( ii )

Given the information below, determine the following:
(i) Processing sequence using (1) SPT and (2) EDD.
(ii) Average flow time and average job lateness using (1) SPT and (2) EDD.
\table[[Job,Processing Time (hours),Hour (due)],[A,17,15],[B,10,25],[C,5,20],[D,7,32],[E,11,38]]