Question: Given the information below, draw the network (AOA) and find the probability of finishing the job in (40) weeks? Solve using PERT. Activity A B

 Given the information below, draw the network (AOA) and find the

Given the information below, draw the network (AOA) and find the probability of finishing the job in (40) weeks? Solve using PERT. Activity A B D EF G Weeks 2,7,8 5,6,9 3,7,8 4,5,6 6,9,10 6,8,11 4,6,7 5,7,10 4,8,9 4,7,9 Preceding A . A B D E F,GI HI 5,6,9 6,9,10 3 6 E B 3,7,8 5,7,10 H 4,8,9 7 2.7.8 6,8,11 4,7,9 1 4 8 9 A F D G 4,5,6 4,6,7 5