Question: Given the information (below) for a two-year project, answer the following questions. Remember the following terms; planned value (PV), earned value (EV), actual cost (AC),
Given the information (below) for a two-year project, answer the following questions. Remember the following terms; planned value (PV), earned value (EV), actual cost (AC), and budget at completion (BAC).
PV
=
$83,000
EV
=
$90,000
AC
=
$96,000
BAC
=
$190,000
a)Explain why earned value management is the preferred method for measuring project performance?
b)Use the formulas provided inTable 2, to calculate the cost variance (CV), schedule variance (SV), cost performance index (CPI), and schedule performance index (SPI) for the project.
c)How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?
d)Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?
e)Use the SPI to estimate how long it will take to finish this project.
Table 2: Earned Value Formulas
Term
Formula
Earned value
EV = PV to date X% complete
Cost variance
CV = EV - AC
Schedule variance
SV = EV - PV
Cost performance index
CPI = EV / AC
Schedule performance index
SPI = EV / PV
Estimate at completion
EAC = BAC / CPI
Estimated time to complete
Original time estimate / SPI
[1+1+1+1+1=5 marks]
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
