Question: Given the information provided below, the expected duration of the project is: 8 B 9 2 O a. 12 O b. 15 OC 19 O





Given the information provided below, the expected duration of the project is: 8 B 9 2 O a. 12 O b. 15 OC 19 O d. 22 Oe. 27Given the information provided below, the latest finish time for activity D is: B E 9 9 2 O a. 12 O b. 13 O c. 19 O d. 22 O e. 27Given the information provided below, the latest start time for activity C is: B 9 9 2 O a. 4 Ob. 5 O c. 12 O d. 13 O e. 19Given the information provided below, the critical path is: B E 9 9 2 O a. A-B-D-G O b. A-C-F-G C. A-C-D-F-G O d. A-C-D-G De. A-B-E-G