Question: Given the network diagram, fill in the resource loading chart. Calculate the total resource load per day in the bottom row. 2. Considering your computations
Given the network diagram, fill in the resource loading chart. Calculate the total resource load per day in the bottom row.

2. Considering your computations in the previous question, what is the project's critical path?
Select one:
a. B-D-F
b. B-E-F
c. A-C-F
d. A-D-F
3. Considering your computations in the previous question, what is the maximum number of resources required on the project?
4. Considering your computations in the previous question, what is the minimum number of resources required on the project?
4 7 4 3 4 83 11 2 2 0 A 4 2 22 2 4 6 6 D 11 0 2 0 6 5 11 11 F 14 0 3 0 11 3 14 0 B 6 0 30 6 6 0 6 E 10 1 1 1 7 4 11 ES ID EF SL RES SL LS DUR LF 1 2. 3 4 5 6 7 7 DO 8 9 10 11 12 13 14 A Resource loading chart ID RES DUR ES LF SL A 2 4 0 6 2 B 3 6 0 6 0 C 3 3 4 11 4 D 2 5 6 11 0 1 4 6 11 1 3 11 14 0 D 2. E F 3 3 Total resource load 00000000000000 4 7 4 3 4 83 11 2 2 0 A 4 2 22 2 4 6 6 D 11 0 2 0 6 5 11 11 F 14 0 3 0 11 3 14 0 B 6 0 30 6 6 0 6 E 10 1 1 1 7 4 11 ES ID EF SL RES SL LS DUR LF 1 2. 3 4 5 6 7 7 DO 8 9 10 11 12 13 14 A Resource loading chart ID RES DUR ES LF SL A 2 4 0 6 2 B 3 6 0 6 0 C 3 3 4 11 4 D 2 5 6 11 0 1 4 6 11 1 3 11 14 0 D 2. E F 3 3 Total resource load 00000000000000