Question: Given the network in Figure below, the critical path is a . A , C , F , H b . B , D ,

Given the network in Figure below, the critical path is
a.
A,C,F,H
b.
B,D,E,F,H
c.
A,C,E,G,H
d.
B,D,E,G,H
e.
B,D,G,H