Question: Given the network plan that follow, compute the early, late, and slack times. What is the project duration? The time - constrained length of the
Given the network plan that follow, compute the early, late, and slack times. What is the project duration?
The timeconstrained length of the project is:
Without regard to resources, what is the slack for Activity Activity Activity
Using any approach you wish eg trial and error develop a loading chart for resources carpenters C and electricians E Assume only one carpenter is available and two electricians are available.
Given your resource schedule, compute the early, late, and slack times for your project. What is the project duration now?
The project duration
Which activities are now critical? You may select more than one answer, Single click the box with the question mark a wrong answer. Any boxes left with answer and double click the box with the question mark to empty the box for a wrong answer. Any boxes left with a question mark will be automatically graded as incorrect.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock