Question: Given the PDM network shown below for typical floors ( 1 to 6 ) of a multi - story building and the duration per floor
Given the PDM network shown below for typical floors to of a multistory building and the duration per floor for each repetitive task, draw a linear schedule for the typical floor tasks according to following scenario Identify and label your lines clearly:
The direction of flow of all crews is "Upward"
Interruption allowed only for the following activities:
Activity to be interrupted once after completing the Floor, if needed.
Activity to be interrupted once after the Floor, if needed.
Buffers:
There is floor stage buffer between Activity and Activity
There is floor stage buffer between Activity and Activity
Please fill in chart
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
