Question: Given the PDM network shown below for typical floors ( 1 to 6 ) of a multi - story building and the duration per floor

Given the PDM network shown below for typical floors (1 to 6) of a multi-story building and the duration per floor for each repetitive task, draw a linear schedule for the typical floor tasks according to following scenario (Identify and label your lines clearly):
The direction of flow of all crews is "Upward"
Interruption allowed only for the following activities:
Activity "B" to be interrupted once after completing the 3rd Floor, if needed.
Activity "F" to be interrupted once after the 4th Floor, if needed.
Buffers:
There is 3 floor (stage) buffer between Activity "E" and Activity "D"
There is 2 floor (stage) buffer between Activity "F" and Activity "G"
Please fill in chart
Given the PDM network shown below for typical

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!