Question: Given the product tree diagram and develop a material requirements plan for item D . A 450 unit-delivery of product P is due at the
- Given the product tree diagram and develop a material requirements plan for item D. A 450 unit-delivery of product P is due at the beginning of week 7. Use the worksheet on the next page. (10 pts.)

| Week# | Beg. Inv. | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| Quantity |
|
|
|
|
|
|
| 450 |
| Item: P
LT= wk
Lot size = | Gross requirements |
|
|
|
|
|
|
| 450 |
| Scheduled receipts |
|
|
|
|
|
|
|
| |
| Projected on hand |
|
|
|
|
|
|
|
| |
| Net requirements |
|
|
|
|
|
|
|
| |
| Plannedorder receipts |
|
|
|
|
|
|
|
| |
| Plannedorder releases |
|
|
|
|
|
|
|
|
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts