Question: Given the project activity information provided below: a) Draw the project network. b) What is the critical path? Activity (ID) Description Preceding Activity Activity
Given the project activity information provided below: a) Draw the project network. b) What is the critical path? Activity (ID) Description Preceding Activity Activity Time (DUR) (days) 1 Requirements None 28 Architecture 1 22 3 Design C 2 16 4 Design S 2 12 5 Design M 2 9 6 Coding U 3 10 Coding T 4,5 8 8 Coding N 5 6 Integration I 6,7 5 10 Integration J 7,8 4 11 System 9,10 10