Question: Given the project information below, complete the missing entries in the table. ML. (m) Pess. (b) te Variance Critical Opt. (a) 16 19 28 30




Given the project information below, complete the missing entries in the table. ML. (m) Pess. (b) te Variance Critical Opt. (a) 16 19 28 30 30 30 0 30 73 60 72 90 25 18 28 30 17 29 47 30 25 X 4 7 10 7 1 Activity Description Predecessor 1 Codify accounts None 2 File articles of unification None 3 Unify price and credit policy None 4 Unify personnel policies None 5 Unify data processing 1 6 Train accounting staff 1 7 Pilot run data processing 15 8 Calculate P&L and balance sheet 6,7 9 Transfer real property 12 10 Train sales force 3 11 Negotiate with unions 4 12 Determine capital needs 8 13 Explain personnel policies 11 14 Secure line of credit 9. 12 15 End 10. 13, 14 13 15 18 6 12 24 13 9 X 18 27 30 26 4 35 35 25 97 100 55 60 100 20 40 11 14 20 29 20 9 X 23 26 22 4 16 19 16 13 0 1 0 0 0 0 Compute the expected project duration. (Round the final answer to the nearest day.) Expected project duration (Note: For the next three questions, use the nearest whole day for expected project duration, but do not round any other intermediate calculations. Your final answers should be in decimal format, rounded to 3 decimal places, i.e., 0.750.) What is the probability of completing the project by day 112? The probability of completing the project by day 112 Within 117 days? The probability of completing the project Within 117 days What is the probability of completing Negotiate with Unions" by day 81? The probability of completing "Negotiate with Unions" by day 81 Click for Z values and probabilities table. Z Value TABLE AT 2 z Values and Probabilities 2.8 -2.6 Probability 2001 .003 2005 .008 ,014 .023 z Value +0.0 +0.2 +0.4 +0.6 +0.8 +1.0 +1.2 +1.4 +1.6 +1.8 +2.0 +2.2 +2.4 Probability .500 579 .655 1726 788 841 1036 885 919 4 055 081 115 -1.2 1.0 0.8 -0.6 -0.4 40.2 212 274 345 421 945 964 977 .986 1992 .995 +2.6 +2.8 997 Given the project information below, complete the missing entries in the table. ML. (m) Pess. (b) te Variance Critical Opt. (a) 16 19 28 30 30 30 0 30 73 60 72 90 25 18 28 30 17 29 47 30 25 X 4 7 10 7 1 Activity Description Predecessor 1 Codify accounts None 2 File articles of unification None 3 Unify price and credit policy None 4 Unify personnel policies None 5 Unify data processing 1 6 Train accounting staff 1 7 Pilot run data processing 15 8 Calculate P&L and balance sheet 6,7 9 Transfer real property 12 10 Train sales force 3 11 Negotiate with unions 4 12 Determine capital needs 8 13 Explain personnel policies 11 14 Secure line of credit 9. 12 15 End 10. 13, 14 13 15 18 6 12 24 13 9 X 18 27 30 26 4 35 35 25 97 100 55 60 100 20 40 11 14 20 29 20 9 X 23 26 22 4 16 19 16 13 0 1 0 0 0 0 Compute the expected project duration. (Round the final answer to the nearest day.) Expected project duration (Note: For the next three questions, use the nearest whole day for expected project duration, but do not round any other intermediate calculations. Your final answers should be in decimal format, rounded to 3 decimal places, i.e., 0.750.) What is the probability of completing the project by day 112? The probability of completing the project by day 112 Within 117 days? The probability of completing the project Within 117 days What is the probability of completing Negotiate with Unions" by day 81? The probability of completing "Negotiate with Unions" by day 81 Click for Z values and probabilities table. Z Value TABLE AT 2 z Values and Probabilities 2.8 -2.6 Probability 2001 .003 2005 .008 ,014 .023 z Value +0.0 +0.2 +0.4 +0.6 +0.8 +1.0 +1.2 +1.4 +1.6 +1.8 +2.0 +2.2 +2.4 Probability .500 579 .655 1726 788 841 1036 885 919 4 055 081 115 -1.2 1.0 0.8 -0.6 -0.4 40.2 212 274 345 421 945 964 977 .986 1992 .995 +2.6 +2.8 997