Question: Given the project information in the following table, what is the probability of completing the project in 5 8 days? Activity Predecessor Optimistic ( a

Given the project information in the following table, what is the probability of completing the project in 58 days?
Activity
Predecessor
Optimistic (a)
Mosk Likely (m)
Pessimistic (b)
None
17
29
47
24
A
6
12
19
28
C
16
16
19
13
14

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!