Question: Given the project information in the following table, what is the expected time to accomplish the Secure patent activity for the Pina Colada Bratwurst Project?

Given the project information in the following table, what is the expected time to accomplish the "Secure patent" activity for the Pina Colada Bratwurst Project?
Act. ID
Description
Predecessor
Optm (a)
Most Likely (m)
Pess. (b)
1
Design package
None
6
12
24
2
Design product
1
16
19
28
3
Build package
1
4
7
10
4
Secure patent
2
24
27
36
5
Build product
2
17
29
47
6
Decorate
3,4,5
4
7
10
7
Test Market
6
13
16
19
Question 12 options:
29
28
30
27

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!