Question: Given the project network and baseline information below, complete the form to develop status reports for periods 1-4. Report the final SV, CV, CPI, and



Given the project network and baseline information below, complete the form to develop status reports for periods 1-4. Report the final SV, CV, CPI, and PCIB. 012 1 1 24 4 1 1 325 1 23 23 35 5 576 0 0 0 0 0 0 o 33 3 2 5 516 0 32 LEGEND ES ID EF SL SL 265 0 0 O 0 O N 2 2 3 5 LS DUR LF Schedule information WP DUR ES LF SL Baseline budget needs (5000) Total Time period PV o 1 2 3 4 5 1248 15 375 8 4 6 1 2 0 3 2 3 0 3 3 2 0 2 4 4 2 2 5 -100-oOo 3 3 5 2 3 5 U18 000 6 6 3 2 5 3 3 3 7 1 5 6 5 Total PV by period 11 Cumulative PV by period 11 19 11 12 75 30 41 53 60 65 Answer is complete but not entirely correct. SPI 1.48 Performance Indexes Summary Period EV 1 16.30 2 28.10 3 37.25 4 49.80 EACE 53.07 AC 15.00 35.00 47.00 60.00 0.94 PV 11.00 30.00 41.00 53.00 VACE CPI 1.09 0.80 0.79 0.83 PCI-B 25.08 43.23% 57.31% 76.62 0.91 0.94 = 11.93
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock