Question: Given the project network and baseline information below, complete the form to develop status reports for periods 1-4. Report the final SV, CV, CPI, and

 Given the project network and baseline information below, complete the formto develop status reports for periods 1-4. Report the final SV, CV,CPI, and PCIB. 0 1 2 2 4 4 1 1 23 3 2 5 2 3 3 5 5 5 7 60 0 0 3 3 3 2 5 5 1 6 LEGEND3 2 2 6 5 ES ID EF 0 0 0 SL
SL 0 2 2 2 3 5 LS DUR LFSchedule information Baselinebudget needs ($000) ACT/ DUR LF Total ES SL Time period WPPV 0 1 2 3 4 5 6 2 3 1 124 8 2 3 3 0 15 3 7 5 3 22 O 8 4 4 4 2 2 5 6 3 35 2 3 5 0 10 6 4 6 3 2 5

Given the project network and baseline information below, complete the form to develop status reports for periods 1-4. Report the final SV, CV, CPI, and PCIB. 0 1 2 2 4 4 1 1 2 3 3 2 5 2 3 3 5 5 5 7 6 0 0 0 3 3 3 2 5 5 1 6 LEGEND 3 2 2 6 5 ES ID EF 0 0 0 SL SL 0 2 2 2 3 5 LS DUR LFSchedule information Baseline budget needs ($000) ACT/ DUR LF Total ES SL Time period WP PV 0 1 2 3 4 5 6 2 3 1 12 4 8 2 3 3 0 15 3 7 5 3 2 2 O 8 4 4 4 2 2 5 6 3 3 5 2 3 5 0 10 6 4 6 3 2 5 0 9 3 3 3 7 1 5 6 O 5 5 Total PV by period 11 19 11 12 7 5 Cumulative PV by period 11 30 41 53 60 65[Do not round intermediate calculations. Enter all answers to 2 decimal places. For SPI. CPI, and PCl-El. enter your answers decimals rather than percentage format (e.g., enter 0.93 instead of 9396].} 3 Cumulative Totals \fEnd of Period 4 Task Actual % Complete EV AC PV CV SV 1 100 13.00 2 100 17.00 3 100 12.00 100 6.00 5 40 2.00 80 7.20 9.00 (1.80) 7 0 0.00 0.00 0.00 Cumulative Totals

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!