Question: Given the project network (legend) and baseline information, complete the status report for the project at the end of period 4 and the end of

Given the project network (legend) and baseline information, complete the status report for the project at the end of period 4 and the end of period 8. From the data you have collected and computed for periods 4 and 8, what information are you prepared to tell the customer about the status of the project at the end of period 8?

Legend:

Project Network Diagram

Baseline Information:

Answer by Completing this Status Report

End of Period 4

Task Actual % Complete EV$ AC$ PV$ CV$ SV$
A Finished ? 300 400 ? ?
B 50% ? 1000 800 ? ?
C 33% or 1/3 of the Budget ? 500 600 ? ?
D 0% ? 0 ? ? ?
E 0% ? ? ? ? ?
Cumulative Totals ? ? ? ? ?

End of Period 8

Task Actual % Complete EV$ AC$ PV$ CV$ SV$
A Finished ? 300 400 ? ?
B Finished ? 2200 2400 ? ?
C Finished ? 1500 1500 ? ?
D 25% ? 300 0 ? ?
E 33% or 1/3 of the budget ? 300 ? ? ?
F 0% ? 0 ? ? ?
Cumulative Totals ? ? ? ? ?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!