Question: Given the project network shown below, 10 points Save Answer and a project variance (critical path variance) of 4, what would be the probability of

Given the project network shown below, 10 points Save Answer and a project variance (critical path variance) of 4, what would be the probability of completing the project in 17 days time (Tc)? Hint: Z= (TC-Tel/Project standard deviation. Use a standard normal distribution table. Pick the closest answer from the options provided below. 0.4567 0.9345 0.8413 0.7856