Question: Given the project network that follows, complete the bar chart for the project. Use the time line to align your bars. Be sure to use

Given the project network that follows, complete the bar chart for the project. Use the time
line to align your bars. Be sure to use the legend to show total float for the non critical
activities.
a. Compute the ES, EF, LS and LF for each activity
b. Compute early and late times (forward and backward pass)
c. Calculate total and free floats
 Given the project network that follows, complete the bar chart for