Question: Given the project plan shown below, for each task assume that the best case duration is 8 0 % of the most likely duration, and

Given the project plan shown below, for each task assume that the best case duration is 80% of the most likely duration, and the worst case duration is 150% of the most likely duration. What is the expected completion time for the critical path?
B.21.0 days
C.35.7 days
D.22.1 days