Question: Given the project plan shown below, for each task assume that the best case duration is 8 0 % of the most likely duration, and
Given the project plan shown below, for each task assume that the best case duration is of the most likely duration, and the worst case duration is of the most likely duration. What is the expected completion time for the critical path?
B days
C days
D days