Question: Given the project within the table below, calculate the following: ActivityPredecessorTime ( days ) A - - 7 . 5 B - - 9 .
Given the project within the table below, calculate the following:
ActivityPredecessorTime daysABCDA CEDFB EGFHG
a What is the project length? Select days", days", days", days", days"
b What activities are on the critical path? Select C D E F G HA B C D E F G HA D E F G HB F G HA C D E F G H
c How much slack is in activity A Select days", days", it is on the critical path", days", days" and activity B Select days", days", days", days", days"
d What is the Late Start Late Finish for activity B Select and and and and and
e What would happen to the overall project length of activity E was delayed by days, now taking a total of days? Select the project length will now be days", "the project length would remain the same", "the project time would be reduced by days because of E having days of slack", "the project length would remain the same, but c would now be on the critical path", "the project length will now be days"
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock