Question: Given the project within the table below, calculate the following: ActivityPredecessorTime ( days ) A - - 7 . 5 B - - 9 .

Given the project within the table below, calculate the following:
ActivityPredecessorTime (days)A--7.5B--9.5C--10.5DA, C8ED10FB, E4GF9HG11.5
a. What is the project length? [ Select ]["53.0 days", "52.5 days", "51.0 days", "47.5 days", "48.5 days"]
b. What activities are on the critical path? [ Select ]["C, D, E, F, G, H","A, B, C, D, E, F, G H","A, D, E, F, G, H","B, F, G, H","A, C, D, E, F, G, H"]
c. How much slack is in activity A?[ Select ]["3.0 days", "5.0 days", "0- it is on the critical path", "19.6 days", "7.5 days"], and activity B?[ Select ]["19.5 days", "22.6 days", "0 days", "6.7 days", "11.4 days"]
d. What is the Late Start / Late Finish for activity B?[ Select ]["19 and 28.5","16.5 and 27.8","22.6 and 26.3","16.3 and 26.3","0 and 9.7"]
e. What would happen to the overall project length of activity E was delayed by 4 days, now taking a total of 14 days? [ Select ]["the project length will now be 57 days", "the project length would remain the same", "the project time would be reduced by 4 days because of E having 4 days of slack", "the project length would remain the same, but c would now be on the critical path", "the project length will now be 53.7 days"]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!