Question: Given the projected demands for the next six months, prepare a level aggregate plan that uses inventory, regular time, and overtime. Regular time is 150

Given the projected demands for the next six
Given the projected demands for the next six months, prepare a level aggregate plan that uses inventory, regular time, and overtime. Regular time is 150 units per month. Overtime can be used as needed. Overtime cost is $30 per unit per period, inventory holding cost is $5 per unit per period, and regular time cost is $20 per unit per period. There is no beginning inventory. Month Demand Forecast Jan 180 Feb 150 March 140 April 150 May 130 June 150 Overtime used for February is 0-5 15-20 o 25-30 0 35-40 None of the above