Question: Given the resources allocated by the aggregate plan, an operations manager develops a weekly schedule for producing a specific product. Which of the following is

Given the resources allocated by the aggregate plan, an operations manager develops a weekly schedule for producing a specific product. Which of the following is the grinstions manager creating? O A. aggregate schedule O B. master schedule O C. short-term schedule O D. breakdown schedule