Question: Given the schedule and time for completion of a project: Immediately Preceding Hours needed to perform the task Task 1 2 3 4 5

Given the schedule and time for completion of a project: Immediately Preceding Hours needed to perform the

Given the schedule and time for completion of a project: Immediately Preceding Hours needed to perform the task Task 1 2 3 4 5 6 7 8 9 1 1 2 2,3 4 2,3 4,5 6,7,8 Tasks 9 7 4 5 7 3 2 4 6 (1) Draw PERT diagram (2) Find the Critical path to complete the project (3) What is the minimal number of hours needed to complete the project?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

1 PERT Diagram 9hrs 9hrs 7hrs 2 Critical Path is ... View full answer