Question: Given the schedule of a project activities below, answer the following questions: table[[Activity,Immediate Predecessors,Duration],[A,-,6,],[B,-,4,],[C,-,8,],[D,A,10,],[E,B,8,],[F,C,15,],[G,D,E,F,10
Given the schedule of a project activities below, answer the following questions: \table[[Activity,Immediate Predecessors,Duration],[A,-,6,],[B,-,4,],[C,-,8,],[D,A,10,],[E,B,8,],[F,C,15,],[G,D,E,F,10