Question: Given the small project for an AOA network:Activity: A , B , C , D , EImmediate Predecessor ( s ) : D , D

Given the small project for an AOA network:Activity: A, B, C, D, EImmediate Predecessor(s): D, D, AB, None, DTime Duration (days): 7,6,5,4,13How many dummy arc(s) in this AOA network should be there totally? Select one: A.0B.4C.1D.2E.3