Question: Given the table below: Activity A B C D E F G Dependency A B B C D E,F Duration (weeks) 10 30 30
Given the table below: Activity A B C D E F G Dependency A B B C D E,F Duration (weeks) 10 30 30 22 20 32 20 Max Crash Time (weeks) N/A 1 3 3 5 3 2 Total Crash Cost ($000,000) 8 30 18 10 9 14 If the indirect cost savings is $2,200,000 per week a) Provide the steps and process to crash this project b) What is the maximum time that this project can be crashed,what is the cost, and what is the new duration? c) Provide the final network diagram (using the maximum crash time)
Step by Step Solution
3.32 Rating (152 Votes )
There are 3 Steps involved in it
The objective of crashing a project is to reduce the project duration at the minimum possible cost This is often necessary when there are incentives f... View full answer