Question: Given the table below: Activity Dependency Duration Resources A 2 3 B A 6 4 C A 8 8 D A 4 6 E B

Given the table below:

Activity

Dependency

Duration

Resources

A

2

3

B

A

6

4

C

A

8

8

D

A

4

6

E

B

3

4

F

B,C

12

2

G

C,D

4

7

H

G

6

9

I

E,F,H

3

2

Develop the project schedule

Build the Gantt chart

Assuming there are only 15 resources available for the duration of this project, how can the schedule be adjusted to level the resources? Revise the Gannt chart to reflect this resource availability.